Notes that I remember from yesterday include:
•First piece of steel is scheduled to go up the 29th of this month.
•They are ahead of schedule and are looking to accelerate construction wherever they can.
•They are starting from the break run area and working their way around the ride.
•The transfer track after the station doesn't count as a block.
•The lift hill alone is going to be 63 seconds to the top.
•One magnetic trim will be in the layout itself, not specified where.
•The footers are up to 22 feet and deeper in some places.
•It will have seat belts that are the same as Intimidator.
•You board on the side closer to the park, and exit towards Hurler.
•Its going to take 2 cranes to assemble the massive crane for the lift hill.
•They said that there are some things missing and different from the animations, specifically the bridge will look different from the animation.
•When the north gate is closed they will use the south gate and a temporary north gate through the picnic shelters.
My friend recorded the whole construction tour q/a and will upload it to youtube for you guys soon.