I'm still wondering why the bottom of the drop was constructed before the lift...
User avatar
By DavidW
#65883
they did the same thing with Leviathan. they build up both directions on the lift/drop, then put in the 4 track peak section last.

Edit: I'm shocked no one has said anything about the 2 pieces of that that have been installed today.... so much for the sequential order.
User avatar
By FamousAmos
#65886
I was watching the animation for Fury and I looked at how the track sections at the top are. There are two curved sections at the top and one straight section after the support. One crane will need to hold the straight section and the other will need to lift the curved sections in place while also holding the basket. Unless a third large crane is built.

EDIT
DavidW, I just noticed that. Perhaps they are trying to get other sections out of the way while they can.
User avatar
By coasterbruh
#65888
DavidW wrote:Edit: I'm shocked no one has said anything about the 2 pieces of that that have been installed today.... so much for the sequential order.

Maybe they're scared to... :wave:
By uscbandfan
#65889
Kind of interesting watching the people walk up and down new, upper section of the lift hill. Looks like the most interesting thing going on now is hand-rail construction on the new section.
By HavenHamilton
#65890
chknwing wrote:looking at the front gate cam there appears to be a piece of track installed behind the trees. maybe thats what you were talking about. shrugs

Image


I was just getting ready to post the same thing. I think it is a new piece of track.
User avatar
By coasterbruh
#65897
Well...thinking about it, it kinda makes sense to start work up there now and work around the coaster. And besides, we get to see the area where most of the excitement of the coast takes place constructed...but you never know what may go up next! :wave: