that track piece their messing with appears to be the one that goes under the bridge. and its going in now.
kirkgun wrote:yay!
I think they're starting to install track again.
My estimated timeline for construction is more like:
by Feb 7 all track pieces are installed
by Feb 28 all track bolts are torqued and station is functionally ready (if not cosmetically) and is ready for the trains
by Mar 7 trains are installed and testing begins
by Mar 28 we all get our chance to enjoy this beast
tylerSC wrote:I wonder why there is no large support pole under the crest of the 325ft lift hill. Kind of nervous that only a few screws and bolts are holding that thing together. But the ALT video pointed out that B&M engineered it to have minimal supports. Is Leviathan designed in a similar manner?
theintimidator wrote:Do the people who where invited to the announcement back in August get to go to the media day event?