- March 4th, 2015, 11:31 am
#71741
Having commissioned several rides before, a majority of the initial testing takes place at night, especially in situations like this, when the area around a coaster is still an active construction zone. Construction workers typically get priority to work during daylight hours, while the ride engineers/those responsible for testing carry out their work at night.
Clearly they've been doing minimal testing around the station already, but don't be surprised if we don't see the first full circuit testing for several more days. Of course, I'd love to be wrong, but by the looks of the several construction workers on the bridge and in the pit/tunnel itself, I'm not holding my breath.