Assuming it is a B&M hyper, which I'm 90% sure it is, the two biggest projects will be to finish any ground moving first and then dig up any areas requiring electric, water/sewage and rerouting of anything.
If they build a splashdown, they first will have to install drainage and piping and then dig the pit, and they also have a lot of boulders to move out of the way, too..
Knowing what I know about Diamondback, and given the warmer climate down there, you'll fist see station prep and additional clearing in the next few weeks, then footer digging quite soon after. With our Diamondback, they had to have some footers done prior to opening day because some were right on the midway, and it looks like there will be little to no interference with public areas for this ride.